Installation Guide of Geotec Grid Reinforcement of Earthwork Construction

 

Input Date::[2011/1/17 9:02:32]    From:Geosyntech Co.,Ltd.

 
1. Preparation of the sub-base surface

Before installing the geogrid, the sub-base surface must be prepared according to location and height and must be  compacted. Tree root residues, stones and other objects that may damage the  geosynthetic product insert or that may have negative effects on its functions  must be removed from the bed in advance. The usual demands on the  preparation of sub-base surfaces must be adhered to, too.
The installation direction is specified in the planning documents. When dealing  with the uniaxial GeotecGrid, the main pulling direction follows the black bars.  The biaxial GeotecGrid, can be strained equally in longitudinal and lateral
direction. 

The geogrid sheets must be installed smoothly and, if necessary, be weighted  by hand using packing material in order to prevent them slipping or being blown  away. 

The geogrids must be installed without overlapping in the strain direction in  supporting constructions or on embankments. If this is unavoidable, separate  validation of the overlapping must be provided. 

When dealing with reinforcement of unbound supporting layers in road  construction, the overlap must be at least 50 cm in normal circumstances and  at least 1.00 m in every direction if the subsurface is very soft. 

2. Installation of the fill material

The granular distribution of the mineral substance mixture in the supporting  layer material must be aligned with the geogrid reinforcement. High water  content should be expected, especially in cohesive soils, which may fluctuate  significantly, depending on the season. Accordingly, the proportion of fine  components < 0.063 mm should be restricted to no more than 5 % of the weight,  in order to enable smooth water drainage without significant pressure. 
This requirement must be defined to an even stricter degree when dealing with  recycling construction materials and recycling construction material mixtures,
where the proportion of fine components < 0.063 mm must be considerably less  than 5 % of the total weight.

Once installed, the geogrids have to be prevented from being directly driven on.  An at least 20 to 30 cm thick layer of supporting material must be installed and  compacted in front-spread method before the surface can be exposed  to traffic.The thickness of the first layer must in this be aligned to suit the  granular composition of the supporting layer material and may therefore be
larger. 
 
3. Compaction and compaction control

In order to ensure that the supporting layer material can be easily compressed  and to prevent the mixture from breaking down, the water contents in the  supporting layer material must be optimized.  A combination of initial static  followed by dynamic rolling procedures has proven to be favourable.  In order  to ensure that the reinforcing effects of the geogrid are activated as soon as  possible, it is advisable to start the compaction process in the middle of the  structure and to then work outwards to the edges. 

Whenever possible, the frequency of the compaction equipment should be  within the range of the characteristic frequency of the sub-base/sub-structure.

The thickness of the individual fill layers must be in line with the sub-base/sub-structure, the installed material and the equipment available for compaction. 

Driving over the installed and compacted supporting layer is a good method  to monitor and confirm the systems load-bearing capacity. The observation of  deformation on the surface of the ground enhancement layer in those areas  that the wheel load passes, and the depths of the tracks enable an initial,  rough assessment of the load-bearing capacity of the construction and the effectiveness of the geogrid in  dependence on the sub-base/sub-tructure. 

An unchanged depth of tracks along the entire route is an indication for even  quality of the installation up to that point. Pumping under the load reveals the  reaction of the sub- base/sub-structure. In such cases, a series of additional plate bearing or CBR tests  permits an evaluation and qualitative assessment. 
 